Completing a geothermal project involves the skills and expertise of a number of professionals. Along with the drilling team, others involved are the heating and cooling contractor, environmental engineers, inspection teams, and local utility representatives. Coordination of both large and small-scale projects requires the experience and in-depth knowledge of all aspects of the job. Ortman Drilling has over 400 years of industry experience that work through a defined process that ensures the project is completed on time and on budget, and with all safety and environmental considerations addressed.
| 1. | Secure project plans, specifications and permits |
| 2. | Complete the submittal process for specified materials and equipment |
| 3. | Call for underground utility locations |
| 4. | Mobilize manpower, materials and equipment to the job site |
| 5. | Set up and drill the geothermal borehole |
| 6. | Install the HDPE loop piping to specified depth |
| 7. | Grout the piping in place |
| 8. | Complete pressure testing of geo-loop piping |
| 9. | Tie in vertical and horizontal piping to system and structure |
| 10. | Complete pressure testing & flushing of system |
| 11. | Final project clean up and demobilization |
| 12. | Closeout procedures and documentation for state agencies |